Extend the Calendar Periods

When extending the calendar periods, you must update the labels and flags simultaneously.

To extend the calendar periods, complete the following steps:

  1. Display the Calendar view of the calendar file that you want to update and select the Calendar Sets tab.
  2. In the Select Calendar Set pane, select Calendar Set 18.
  3. In the Calendar Set pane, delete the At Complete label and the * flag next to the currently tagged period.
  4. Select the new period that you want to tag and add the At Complete label and the * flag.
  5. In the Select Calendar Set pane, select Calendar Set 18 and repeat steps 3 and 4.
  6. Click Close and save your changes.
  7. On the General tab of the Project Properties dialog box, update the Baseline Finish field.