Associate a Budget Class with a Forecast Actual or Earned Class

Use the Included Budget Classes tab of the Classes tab to associate existing budget classes with a specific actual, earned, or forecast class.

To associate a budget class with an actual, earned, or forecast class, complete the following steps:

  1. Display the Project Properties dialog box and select the Classes tab.
  2. Click the Included Budget Classes tab.

    This tab is available only if you selected either the actual, earned, or forecast class on the Classes grid of the Classes Tab of the Project Properties dialog box.

  3. Click Add.
  4. On the Classes Lookup dialog box, select the budget class that you want to associate with the selected actual, earned value, or forecast class.

    You can use to open the Find dialog box, where you can search for budget classes by name.

  5. Click Select to associate the budget class with the selected actual, earned value, or forecast class.
  6. Click Apply on the Included Budget Classes tab.