Access a Dynamic PSR Status Report

To access project status reports, complete the following:

  1. Select the Supplemental Reports module.

  2. Select Project as the management context.

  3. Navigate to the lowest level of the project ID in the project navigation field.

  4. In Reports & Actions, select Project Status » Active Level S.P.A.5 Project Status.

  5. Refer to the following for the parts of the Project Status Report:

bp_pm_dynamic3.gif

bp_pm_dynamic4.gif

  1. Click the + icons to expand the information in the report.

bp_pm_dynamic5.gif

  1. Click the Commitment header to drill down and audit commitment details.

bp_pm_dynamic6.gif

  1. Select options in the Purchase Commitment Detail header.

  2. Click to show PO Commitments.

  3. Click Unposted Labor to see a listing of unposted time sheets.

  4. Select a Period Ending date from the drop-down menu.

  5. Notice the other report header information: Project number, Project Name, Project Manager, Status, Project Type and Period of Performance.

bp_pm_dynamic7.gif

  1. Click any Labor Cost description that is underlined to audit details of expended resources.

bp_pm_dynamic8.gif

  1. Click any Non-Labor Cost description that is underlined to audit details of expended resources.

bp_pm_dynamic9.gif

  1. Click the + icon in the Labor Hours section to expose the details of hours consumed on a project by a labor resource; Employees and Vendors.

bp_pm_dynamic10.gif