The Set Baseline Equal to Earned Value (BCWS = BCWP) option is used to nullify a schedule variance.
Backup your data before performing the replan.
In-process work packages are defined as work packages that have either cumulative BCWS or cumulative BCWP through the replan month.
MPM will perform a replan only if there is cumulative BCWS or BCWP through the replan month on the WBS. If an EOC does not have cumulative BCWS or BCWP through the replan month, that EOC will be skipped during the replan.
The If No Baseline option is not available.
The XREF-EST option is available.
In the following example, there are actuals against only one EOC — Labor.
|
JAN |
FEB |
MAR |
APR |
MAY |
JUN |
BCWS Cum |
10 |
20 |
30 |
40 |
50 |
60 |
BCWP Cum |
5 |
5 |
10 |
10 |
20 |
30 |
Replan *L |
|
|
|
-30 |
|
|
In the example, a new resource estimate (Replan *L) is added to the BCWS for labor and the estimate has only one value (-30), the cumulative difference between BCWP and BCWS. The replan estimate (Replan *L) will contain adjusted values at all costing levels (hours, overhead, etc.) except fee.
If you recalculate BCWP after performing a replan using this scenario, you should specify the month of May as the Calculate BCWP From month to ensure that past history is not changed due to the adjustment to BCWS.