Add Assignments to Selected Resources Dialog Box

Use the Add Assignments to Selected Resources dialog box to assign work on a project to a group of resources that you have selected in Resource View.

Location

To display the Add Assignments to Selected Resources dialog box, complete the following steps:

  1. In the Resource Planning workspace, click to go to the Resource View.
  2. If necessary, use a search to display, in the grid, the resources to which you want to assign work on a project.
  3. Select the check box next to each of the resources you want to include in the group.
  4. Click + Add Assignments on the Resource View toolbar.

Contents

Field Description
Find project or opportunity

Select the project or opportunity for which you want to assign work to the resources.

Click in this field to select the project or opportunity from the full list, enter one character to display and select from a list of projects and opportunities with a name or number/ID that starts with that character, or enter two or more characters to select from a list of projects and opportunities with a name or number/ID that contains those characters.

Only active projects and opportunities are available for selection.

RESOURCE

This grid column displays a list of the resources that you selected in the Resource View grid. If the list includes both employees and generic resources, employees are listed first, followed by the generic resources.

Select the check box next to each resource to which you want to make an assignment. The number selected displays below the grid.

Click the name to display a tooltip containing additional employee or generic resource information. For an employee, you can view job title, organization, labor category, utilization target percentage, hours per day, status, and email address. For generic resources, you can view organization, labor category, and status.

Clear Selections

If you select some resources and then decide you want to clear all of those selections and start over, click Clear Selections.

If no resources are selected, this option does not display.

Hard Book

If you consider the new assignments hard booked, select the Hard Book check box.

This check box is only available if Deltek CRM is configured to use soft and hard booking and if you have the required security access to hard book assignments.

SELECT and LEVEL

This grid displays the WBS hierarchy, along with any existing resource assignments. Expand the hierarchy to display the WBS elements for which you want to assign work to the resources, and select the check box next to each of those elements. (Either WBS element names or both names and IDs display, depending on whether Show WBS Numbers is selected in the Column Settings & Selections dialog box for Resource View.)

You can only assign resources to the lowest-level WBS elements in each branch of the WBS. A check box displays next to those elements. You can also expand lowest-level elements to display any resources that are already assigned to them.

The following do not display as part of the WBS hierarchy:
  • Inactive WBS elements at any level of the hierarchy.
  • Active "parent" elements that have no active "child" elements.
  • Active "child" elements whose "parent" element is inactive.

After you select the resources you want to assign and select the WBS elements to which you want to assign them, click to make the assignments.

These are only pending assignments at this point. The actual assignments and update of the plan occurs when you click the Assign button at the bottom of the dialog box. The number of pending assignments displays next to the Assign button.

After you click , all selections in the WBS hierarchy are cleared, but your selections in the resource grid remain in case you want to assign the same group of resources to other WBS elements. Click Clear Selections under the grid if you want to clear the old selections so you can select a different set of resources.

If you add an assignment and then want to remove that assignment, hover over the resource row in the WBS grid and click at the end of the row.

This option is only available for pending resource assignments. To delete an assignment that was added to the plan previously, use the deletion option in either the Project View grid or the Resource View grid.

Assign Click this button to confirm the assignments, close the dialog box, and update the plan information in the Resource View grid.
Cancel Click this button to discard all pending assignments and close the dialog box.