Budgeting & Planning allows the following types of task statuses:
Milestones with weighted values and/or fixed start/finish formulas (legend details must be provided)
Percent complete
Percent complete constrained by milestone gates (legend details must be provided)
Equivalent units/standards (legend details must be provided)
Apportioned (status is assigned based upon associated WBS element ID)
Level-of-effort (set to BCWS)
In cases where the time-phased budget has not been directly imported from a scheduling application, Budgeting & Planning provides a mechanism to allow the association of each WBS element, as defined by the original request for proposal, with its corresponding accounting system cost account or project/task identifier. Click E.P.I.3 WBS to ProjID Assignment in Reports & Actions to access this functionality.
Click Update once the association has been made.