You are here: Ajera Help (A-Z) > Payroll > Processing payroll in-house > Running certified payroll

Running certified payroll

unavailable in ajeraCore unless you have the Payroll add-on

Before you begin

To run certified payroll

  1. As part of setting up a project, on the Project Info tab > General subtab of the Project Command Center (Setup > Projects), select the Project requires certified PR check box for projects and phases that require a certified payroll report.
Note:
  • Select the check box at both the project level and the phase level.
  • Select the wage rate table for the project or phase, if needed.
  1. As the project proceeds, employees enter time for hourly work on projects in Manage > Time & Expense.
  2. To run payroll, from the Manage menu, click Payroll.
  3. From the Reports menu, click Certified and print the Certified payroll report for the project or date range you want.
Note:

The report prints one week at a time. Print a separate week for other weeks, if needed

See also

About certified payroll

Adding the Certified payroll report to the Reports menu

 

 