Project Earnings report
Use this report to obtain a complete picture of your projects including
billing, cost, and profit.
You can also use it to focus your marketing efforts on the most profitable
project types and fee arrangements. As a principal, you can monitor a
project manager’s profitability and manage the exceptions. The information
on this report includes profit amounts and percent of profit.
You can do the following with this report:
- Review Work-in-progress (WIP)
and Receivables balances.
- See a write-off amount when
the WIP amount has been manually changed or the WIP status has been changed to Write-off
- Optionally include overhead
expenses in your project labor cost
- Print it with labor only,
or include expenses and or consultants
You can summarize information by project manager, principal in charge,
project type, or department. You can drill down to project, phase, and
full detail information.
Note: |
unavailable in ajeraCore - When using Business Development, note that this report includes
amounts for production phases not linked to marketing phases and for production
phases linked to marketing phases with a final disposition of Won. |
Audience
Principal
Project manager
Marketing manager
CPA
Producing the report
From the Reports
menu, click Project > Project
Earnings.
Report options
Company
|
Multi-company only. The report contains information for all companies in your organization, unless you select
a specific company in this field.
|
Project
|
The report contains information for all projects for the period selected,
unless you select a specific project in this field.
|
Customize options
Report title
|
You can change the title of the report.
|
Sort order
|
Sorts the report by project, project manager, billing manager, principal
in charge, project type, client, or department. If you use multi-company, you can also sort by company.
|
Project status
|
Prints all projects or projects of a specific status
|
Include marketing phases
|
unavailable in ajeraCore
If selected, it includes Business Development marketing phases in the report.
|
Limit by
|
Only prints projects associated with the project manager or principal-in-charge
who is producing the report. You can print all projects by selecting
No limit. If you use multi-company, you can also limit by company.
|
Profit basis
|
Includes spent, billed, or billed + WIP in the profit calculation. The
profit amount reflects the profit basis option you select here (spent,
billed, or billed + WIP) minus the cost.
|
Labor detail group
|
Prints the labor detail on the report according to the order you select
|
Expense and consultant detail group
|
Prints the expense and consultant detail according to the order you
select
|
Include premium time in cost
|
If selected, it includes premium time in cost amounts.
|
Print overhead projects
|
If selected, it includes overhead projects in the report.
|
Cap profit at contract amount
|
If the Profit Basis (spent, billed, or billed plus WIP) amount exceeds
the contract amount, the report uses the contract amount to calculate
the profit. Otherwise, it calculates the profit using the Profit Basis
amount selected. Calculations are made for each phase and then summed
for the project total.
|
Hide write-off column
|
If selected, the column for write-off amounts does not appear on the
report.
|
Include overhead in cost
|
If selected, it includes overhead in the cost amount.
|
Include expenses
|
If selected, it includes expense in report amounts.
|
Include consultants
|
If selected, it includes consultants in report amounts.
|
Use drilldown
|
If selected, you can drill down to further detail on the report. If
cleared, all information, including the lowest level of detail, prints
on the report.
|
Print notes
|
If selected, it displays at the detail level notes entered for time
& expense.
|
Print customize options on reports
|
If selected, it prints a list of the options that you select.
|
Report contents
Status
|
The current status, as follows:
A - Active
P - Preliminary
W - Work hold
H - Hold
B - Billing hold
C - Closed
M - Marketing (unavailable in ajeraCore)
|
Contract
|
The contract amount for the project. (This includes
expense/consultants if selected.)
|
Spent
|
The total amount of time and expense expended on the project at the
billing rates/markups. Ajera determines the spent amount from the billing
rate table.
|
Spent %
|
The percent of the contract amount for the project already spent:
% Spent = Spent Amount / Contract Amount
|
Billed
|
The amount already billed for the project. This includes invoices that
have a status of Final or Written-off. It does not include invoice adjustments
or sales tax amounts.
It includes invoice adjustments unless you select the Setup > Projects > Project Info tab > Billing subtab > Exclude from billed for reporting check box for an adjustment.
For Time & Expense projects, this amount equals the billed value
of time (and expense/ consultants if selected) invoiced.
For fee-type projects, this amount equals the fee billed amount.
|
Billed %
|
The percent of the contract amount already billed for the project:
% Billed = Billed Amount/Contract Amount
|
WIP
|
Billable time (and expense/consultant if selected) that has not yet
been included on a Final client invoice
|
Write-Off
|
This amount reflects changes in Manage Client Invoices when:
- You manually change a work-in-progress
detail billed amount.
- You change the status of
WIP to Write-off.
|
AR
|
Receivable amount owed to you. This amount includes
invoice adjustments and sales tax
|
Cost
|
The amount of time (and expense/consultant if selected) that you actually
spent so far to complete the work associated with the billed amount. Includes
cost of premium time if the Include premium
time in cost customize option is selected.
|
Profit
|
The amount that the profit basis (spent, billed, or billed + WIP) exceeds
the cost:
Profit = Profit Basis - Cost Amount
|
Profit %
|
The percent of the billed amount that is profit:
% Profit = Profit Amount/Profit Basis
|
Drilldown - phase:
|
Cost Hours/Units
|
The number of units. Units are measurable items associated with the
cost entry, such as labor hours, blueprints, and mileage.
|
Cost Rate
|
The rate that reflects the actual cost marked up with overhead and profit
multipliers.
For labor, the cost rate is the per hour rate paid to an employee.
For salaried employees, the cost rate is the salary divided by the number
of standard hours in the pay period.
For hourly employees, the cost rate is the regular pay rate.
For expenses, the cost rate is the rate per unit for expenses, such
as mileage, copies, and so on.
|
Cost Amount
|
The amount that you actually spent for work performed, or the out-of-pocket
costs to the company for expenses and consultants. If the cost is associated
with units, the cost equals Hours/Units * Cost Rate. Includes cost of
premium time if the Include premium time
in cost customize option is selected.
|
Spent Rate
|
The rate used to bill the client for work or expenses. Ajera
determines the spent rate from the billing rate table.
|
Spent Amount
|
The total amount of time and expense expended on the project at the
billing rates/markups. Ajera determines the spent amount from the billing
rate table.
|
Billed Hours / Units
|
The number of units billed. These units reflect
any changes made in Manage Client Invoices.
This amount only appears if the detail is included on a final invoice.
|
Billed Rate
|
The rate used to bill the client for work or expenses. Ajera determines
the billing rate from the billing rate table. This rate reflects any changes
made in Client Invoices. This amount only appears if the detail is included
on a final invoice.
|
Billed Amount
|
The amount already billed for the phase. This
amount reflects any changes made in Manage Client Invoices.
It includes invoice adjustments unless you select the Setup > Projects > Project Info tab > Billing subtab > Exclude from billed for reporting check box for an adjustment.
The Billed Amount appears as zero in detail lines on the report when
the phase is billed based on a fee amount. It indicates that you did not
bill the client for individual time and expense because it is a fee-basedThe project or phase is contracted to bill for the value of the work performed, not for the actual time and expenses expended. These projects or phases are identified with a billing type of Fixed Fee, Percent Complete, Unit Price, or Percent of Construction Cost. project.
|
WIP
|
Billable time (and expense/consultant if selected) that has not yet
been included on a Final client invoice
|
Write-Off
|
This amount reflects changes in Manage Client Invoices when:
- You manually change a work-in-progress
detail billed amount.
- You change the status of
WIP to Write-off.
For fee-type projects, the report columns Spent Amount - Billed Amount
- WIP Amount may not equal the Write-off Amount.
|
See also
Producing reports
Using the reports toolbar
|
|