Hours
|
Enter the total hours to-date for this phase. Ajera uses it for project-to-date
hours on management reports.
|
Cost amount
|
Enter the total cost amountThe amount paid to employees for work performed, or the out-of-pocket costs to the company for expenses and consultants. for labor to-date for this phase. Ajera uses it for project-to-date cost
on management reports. If you will use DPE and overhead to mark up labor cost, enter the total of the cost, DPE, and overhead.
|
Spent amount
|
Enter the total spent amount for labor to-date for this phase. Ajera
uses it for project-to-date earned amount on management reports.
Caution: |
Be
sure to exclude the spent amounts for unbilled work-in-progress (WIP) that you enter as
beginning balances for unbilled WIP.
If you do not have a spent amount available to enter, you can do one
of the following instead:
-
Enter the billed amount,
which does not reflect write-offs on project reports.
-
Enter the cost marked up
by overhead and profit percent, which does reflect write-offs on project
reports.
|
|
Billed amount
|
Enter the total billed amount for labor to-date for this phase. Ajera
uses it for the project-to-date billed amount on management reports.
Caution: |
Be
sure to exclude the billed amounts of unpaid client invoices that you
enter as beginning balances for
unpaid client invoices.
If this phase has a billing type of Percent Complete, Unit Price, or
Percent of Construction, you must enter a billed amount for your future
invoices to calculate the correct Percent Billed and Remaining amounts.
|
|
Cost amount
|
Enter the total cost amount for expenses to-date for this phase. Ajera
uses it for the project-to-date cost on management reports.
|
Spent amount
|
Enter the total spent amount for expenses to-date for this phase. Ajera
uses it for project-to-date spent amount on management reports.
|
Billed amount
|
Enter the total billed amount for expenses to-date for this phase. Ajera
uses it for the project-to-date billed amount on management reports.
Caution: |
Be
sure to exclude the billed amounts of unpaid client invoices that you
enter as beginning balances for
unpaid client invoices.
If this phase has a billing type of Percent Complete, Unit Price, or
Percent of Construction, you must enter a billed amount here for your
future invoices to calculate the correct Percent Billed and Remaining
amounts.
|
|
Cost amount
|
Enter the total cost amount to-date for consultants for this phase.
Ajera uses it for the project-to-date cost on management reports.
|
Spent amount
|
Enter the total spent amount for consultants to-date for this phase.
Ajera uses it for the project-to-date spent amount on management reports.
|
Billed amount
|
Enter the total billed amount for consultants to-date for this phase.
Ajera uses it for the project-to-date billed amount on management reports.
Caution: |
Be
sure to exclude the billed amounts of unpaid client invoices that you
enter as beginning balances for
unpaid client invoices.
If this phase has a billing type of Percent Complete, Unit Price, or
Percent of Construction, you must enter a billed amount here for your
future invoices to calculate the correct Percent Billed and Remaining
amounts.
|
|
Units
|
Applies only if the phase has a billing type of Unit Price. Enter the
total units billed to-date for the phase.
|