Elements of Cost Tab of the Activity Details Pane

When you select a control account or work package, this tab displays the values for the five elements of cost (Labor, Material, Other Direct Costs, Subcontrator, None).

When you select a control account, this tab displays the values for the control account only. That is, it doesn't display the sum of the work package values. When you select a work package, it displays the values for the work package only.

Field Description
Element of Cost This column displays the elements of cost:
  • Labor
  • Material
  • Other Direct Costs
  • Subcontrator
  • None (stores values that are not assigned to any of the other four)
Cost/Hours These columns display the following data for each element of cost in both cost and hours:
  • Actual Cost of Work Performed (Cumulative and Current)
  • Budgeted Cost of Work Performed (Cumulative and Current)
  • Budgeted Cost of Work Scheduled (Cumulative and Current)
  • Estimate to Complete
  • Budget at Completion
  • Estimate at Completion