Create the Reporting Calendar in Open Plan Using Cobra's Export Calendar

Use Cobra’s Export Calendar feature to create the reporting calendar in Open Plan.

To create the reporting calendar:

  1. In Cobra, click Integration » Open Plan Calendar.

  2. On the first page of the wizard, select the following values and complete the export.

For more information, see the "Calendar Export to Open Plan" topic in the Cobra Help System.

After creating the reporting calendar, you must assign it to the project in Open Plan. See Assign the Reporting Calendar to the Project in Open Plan.