Switch Resource Display from Hours to Currency Amounts

When you view data on the Resource grid, Vision Navigator displays information in hours for the selected work breakdown structure's resources. You can change this view to display the information by currency amounts.

To switch the resource display from hours to currency amounts, complete the following steps:
  1. On the Vision Navigator Planning Grid header, click .
  2. Select one of the following options:
    Option Description
    Resource Hours Select this option to display the hours for each resource.
    Resource Amounts Select this option to display the hours by currency amounts for each resource.

    A checkmark displays next to your selection. The Baseline, JTD, ETC, and EAC fields update with the hours or amounts. The amounts in these fields are automatically rounded and summed so that the ETC amount for the selected work breakdown structure is the sum of the ETC amounts for each resource.

    The calendar periods on the Resource Assignments Grid Calendar do not update based on the hours or currency selections.

  3. Click Save to update the work breakdown structure amounts.