Resource Assignments Grid Calendar

Use this grid to view the resources assigned to the current plan, by calendar period.

Contents

The lowest level of the Level/Resource column displays any named or generic resources assigned to the project, phase, or task element. Resources who have charged to the project (posted or unposted hours), but do not have planned hours, are listed with the resources who do have planned hours.

Hours in the Resource Assignments grid are formatted based on the settings in Vision's Plan Settings. Options include None, Decimal, and 2 Decimals. If you use the Vision Multicompany feature, the hours setting comes from the Plan Settings of the company to which the project belongs.

Calendar Periods

This grid displays the calendar periods for the selected WBS element's start and end dates. Specifically, it displays the planned hours per period for plans in utilization. For Navigator plans, the calendar scale for the periods is defined in Plan Settings. For Vision plans, the calendar scale defaults to Weekly for WBS elements with date ranges 180 days in length or less; a longer date range results in the use of a Monthly scale.

The calendar periods on the Resource Assignments Grid Calendar do not update based on the hours or currency selections.

Field Description
ETC This column displays the estimate-to-complete hours or billing amount for the resource on the current project, phase, or task. This is the number of hours or the billing amount required from tomorrow through the end of the plan to complete work on this project, phase, or task element.

Calculation: ETC = Planned hours or billing amount from tomorrow forward for plans in utilization