Spread Costs Evenly
You can spread costs evenly over the selected period.
(Spread Amount/Total Business Days) * Cell Business Days
The total business days are the number of business days between the start date and the end date that you specify on the Spread Evenly dialog box.
Spreading cost amounts on the Labor, Expenses, or Consultants planning tabs will update the plan's hours on the accordion calendar on all related Planning tabs. If you change a task's duration on the interactive Gantt chart on the Schedule tab, Vision automatically re-spreads the cost amounts evenly across the new duration on the other Planning tabs. Use caution when changing task dates and durations on these tabs, and when spreading data.
To spread costs evenly, complete the following steps:
- From the Vision Navigation menu, click .
- Open a plan record.
- Click the Labor, Expenses, or Consultants tab.
- Select the date on which you will begin to spread costs. On the Planning grid, right-click a Compensation Cost, Consultant Cost, or Reimbursable Cost cell.
- Click Spread Evenly. The Spread Evenly dialog box displays. The From: field in the Period Range automatically displays the date on which you will begin to spread costs.
- Use the drop-down list in the To: field to select the date on which to stop spreading costs.
- Enter the amount to be spread and click OK.