Labor Plan EVT Charts Columns
The Labor Plan EVT Charts report contains a standard set of columns. You do not have the option to select columns for this report.
Columns
Column | Description |
---|---|
Period in Chart | This column displays the period from chart. |
BCWS | This column displays the budgeted cost of work scheduled for the period.
These amounts are based on planned amounts or on baseline amounts, depending on the option you select in For BCWS, Show on the General tab. |
ACWP | This column displays the actual cost of work performed for the period.
Vision displays graphed values based on actual job-to-date amounts as a solid line and displays graphed values based on estimate-to-complete amounts as a broken line. |
BCWP | This column displays the budgeted cost of work performed for the period. |