EAC and ETC Values
You can enter Estimates at Completion (EAC) and Estimates to Complete (ETC) on the Project Budget Worksheet.
Your ability to work with EAC and ETC values depends on Configuration settings. See your System Administrator if you need assistance.
Value | Description |
---|---|
EAC Hours | Estimate at Completion Hours
Your estimate of the total number of hours expended at the completion of the task or project. |
EAC Amount | Estimate at Completion Amount
Your estimate of the total cost at completion of the task or project. You can enter EAC amounts on the Project Budget Worksheet by:
|
ETC Hours | Estimate to Complete Hours
Your estimate of the total additional hours required to complete the task or project. |
ETC Amount | Estimate to Complete Amount
Your estimate of the total additional cost required to complete the task or project. You can enter ETC amounts on the Project Budget Worksheet by:
|