Schedule Consultant Accruals to Run at Another Time

You can schedule the consultant accruals process to run at a later time.

To schedule consultant accruals to run at a later time, complete the following steps:
  1. From the Vision Navigation menu, click Accounting > Consultant Accruals.
  2. Optional. On the toolbar of the Consultant Accruals form, click Update % and then use the Update Percent Completes dialog box to update percent complete data.
  3. Review and, if necessary, modify data on the Consultant Accruals form.
  4. On the toolbar of the Consultant Accruals form, click Schedule.
  5. On the Schedule dialog box, select a processing queue, enter a description, and specify the date and time that you want the consolidation process to run.
  6. Click OK.
After you process the journal entries, you can post them.