Change Task Dates to ASAP
When you set task dependencies, you can create additional float between a successor and predecessor without adding lag or lead time. To do this, you can change all task dates to ASAP (as soon as possible). When you use the ASAP option, you remove the float before the start of the successor.
Before you change the task dates to ASAP, you must consider the type of relationship that is created between dependent tasks.
Relationship Type | You can manually add float before the start of the successor as long as the successor . . . |
---|---|
Finish to Start | Does not start earlier than the finish date of the predecessor (including any lag/lead time) |
Start to Start | Does not start earlier than the start date of the predecessor (including any lag/lead time). |
Finish to Finish | Does not finish any earlier than the finish date of its predecessor (including any lag/lead time) |
Start to Finish | Does not finish any earlier than the start date of its predecessor (including any lag/lead time). |
To change the task dates to ASAP, complete the following steps:
- From the Vision Navigation menu, click Planning > Project Planning and click the Schedule tab.
-
Select a task, group of tasks, or all tasks:
Option Description To move a single task to ASAP Select the green bar for the task that you want to start as soon as possible. A gray border displays around the selected task. The task's date will move to the earliest start date possible, taking established dependencies into consideration. To move a group of tasks to ASAP at one time, Select the black group level bracket or use the CTRL or SHIFT keys and select more than one task or group. The entire group of tasks will shift but the remaining tasks on the interactive Gantt chart will not, unless there is an established relationship that forces it to shift. To move all tasks to ASAP at the same time Click in an empty space on the interactive Gantt chart or select the project level (bracket). All tasks will move to the earliest start date possible. - Right-click and then select ASAP on the shortcut menu.
Parent Topic: Procedures for Task Dependencies