Dependencies Dialog Box
Use the Dependencies dialog box to view the dependent predecessor or successor tasks for the current row on the Labor grid. This information is useful when you build task dependencies or before you change dates for one or more task rows.
You cannot edit the fields on the Dependencies dialog box. Use the Schedule tab of the Project Planning form to change the relationships between tasks.
Parent Topic: Screens
Location
To display the dialog box, complete the following steps:
- From the Vision Navigation menu, select Planning > Project Planning.
- Click the Labor tab of the Project Planning form.
- Select a grid row where there is a dependency established for the selected task, as indicated by in the Dependency column.
- Right-click and select the Dependencies option on the shortcut menu.
Contents
Predecessor Grid
Use the Predecessor grid to view the defined predecessor tasks.
Successors Grid
Use the Successors grid to view the successor tasks and their relationships.