When you schedule a follow-up activity, it does not replace the existing activity. It adds a related activity to the Activities grid on the Activity Manager form. For example, you can schedule a follow-up phone call with a potential
client.
To schedule a follow-up activity in the Activity Manager, complete the following steps:
-
From the
Vision Navigation menu, click
.
-
On the Activity Manager form, use the Activities Filter dialog box to narrow the activities that display in the Activities grid.
-
On the Activities grid, click the row that contains the activity for which you want to schedule a follow-up activity and click
Edit on the grid toolbar.
-
On the Activity dialog box, complete the following actions:
-
Click the
Create Follow-up Activity toolbar option.
Vision copies the existing activity details to create a new activity.
-
Complete the fields on the Detail tab.
-
Use the tabs to add leads, attendees, and contacts. Select the
Notify Attendees check box on the Attendees tab and/or Contacts tab to send activity notifications to attendee and/or contacts.
-
If this is a recurring activity, click the Recurrence tab and specify a frequency and duration.
-
If you have user defined tabs, click these tabs to add information to the activity.
-
Click
OK to close the Activity dialog box.
Vision inserts the follow-up activity details in the Activities grid on the Activity Manager form.
-
On the Activity Manager form, click
Save to save and schedule the follow-up activity.