Change the Scale for the Calendar Period Columns

In Project View, you can view and enter hours for resource assignments by day, week, or month.

To change the scale for the calendar period columns, complete the following steps:

  1. In the Deltek Resource Planning workspace, click to go to the Project View.
  2. Click next to Scale on the Project View toolbar.
  3. In the Change Scale dialog box, click in SCALE and select one of these options:
    • Days & Months: Display resource plan data by day for one or two months, with the rest of the project plan displayed by month.
    • Weeks: Display all resource plan data by week.
    • Months: Display all resource plan data by month.
  4. If you selected Days & Months, click in USE DAY SCALE STARTING and select the month in which you want to begin displaying plan data by day.
  5. If you selected Days & Months, click in USE DAY SCALE FOR and indicate if you want to display one or two months of plan data by day.
  6. Click Change.

    The calendar period column headings change to reflect your selection, and any existing hours in those columns are recalculated based on the new scale.