Use the Automatically Update Baseline Dates When a Change Causes the Activity Dates to Change option to define the default setting for the PMC Include in Baseline field in Open Plan. If you select this option and the activity change caused an activity date change (for example, adding a target date or changing a duration), the baseline dates of the activity and all associated activities linked to a work package are updated.

You can access this option in the Change Details on Form Tab of Workflow Type Configuration.

During a modeling session, PM Compass uses the Automatically Update Baseline Dates When a Change Causes the Activity Dates to Change option to determine whether or not to update the baseline dates of the activity and all associated activities linked to a work package, depending on the value populated in the PMC Update Baseline Dates field in Open Plan.

When you select the Automatically Update Baseline Dates When a Change Causes the Activity Dates to Change option, the following rules for updating the baseline dates of all associated activities apply:

When you clear the Automatically Update Baseline Dates When a Change Causes the Activity Dates to Change option, but you want to update the baseline dates of all associated activities, you must enter a Yes or Y in the PMC Update Baseline Dates field of all activities for which you want the baseline dates to be updated.

The PMC Update Baseline Dates field defaults to Y or Yes when you perform one of the following: