Activity steps are similar to milestones and can add significant value to project scheduling. A scheduler can assign several steps to an activity and weight each step to apportion its value compared to other steps. Steps allow you to measure the progress of an activity objectively. When a step is completed, the weight on the step is used to calculate the Physical Percent Complete on the activity, which in turn is used to calculate the earned value.
The steps displayed on this tab follow the order defined in the schedule. You can click a column heading to sort the grid, but the sort is not remembered and reverts to the Primavera P6 or Open Plan order when you move to the next activity or return to the view. You cannot insert or delete steps in the grid.
Step notes that are added in Open Plan and Primavera P6 do not display in PM Compass.
All steps are set to Complete/100 % when you:
Enter an activity actual finish date
Progress an activity to complete
This tab is read only and is only visible when the project, or subproject, is linked to a Primavera P6 (or higher) or Open Plan 8.2 (or higher) schedule.
Option |
Description |
Steps |
Click the drop-down arrow to display the following options:
|
Field Name |
Description |
Step Name |
This column displays the name of the step. |
Step Weight |
This column displays the step weight. This field, together with Step % Complete, is used in the Physical % Complete calculation. |
Step Weight % |
This column displays the step weight as a percentage. Since the step weights do not have to add up to 100, use this field to determine the relative weight of the step. |
Step % Complete |
This column displays the percentage complete for the step (for example, 16.32%). |
Completed |
This column displays whether or not the step has been completed. |
Notes |
This column displays the first 100 characters of the notes entered for a step. The notes are displayed as a hyperlink. Click the hyperlink to display the Note dialog box, which you use to view the full notes entered. |