Creating Assignments from the Costs tab

To create the Open Plan resource assignments correctly, you must have the following set up before you start the change request:

When creating the change request, the data entered on the Costs tab is used to calculate offsets and periods for the Open Plan resources assignments using the early start date of the activity and the working days for each period in the time phased view. If the early start date of an activity changes after editing the time phased costs, the offsets and periods will not match the Costs tab. If the duration of the activity is reduced, an error message will display.

To ensure the calculated offsets and periods match the data as entered in the time phased view, the following must occur:

To edit the data on the Costs tab after going to the scheduler, you must click Edit Schedule so that the offsets and periods on the resource assignments can be updated. This will require the scheduler to reapprove the change in Open Plan.

To view the offsets and periods that are created on the resource assignments in PM Compass, you must exit and reopen the Change Details view. The original curve is not preserved in this process.  A resource assignment row is added per period with a linear curve for each period.

What do you want to do?

Add time phased data

Delete time phased data

View time phased resource data for a control account or work package

Edit costs in the time phased grid

Respread costs