Change the EVT for an Activity

Use this procedure to change the EVT for an existing activity.

For more information, see Activities Overview.

To change the EVT for an existing activity:

  1. On the Navigation menu, click Workflows » Change Management » select a Change Request.

  2. In the List View, select the Change Request.

  3. On the General tab of the Change Request Form, click the Change Details button. The Change Details view and barchart displays.

  4. Select the activity whose EVT you wish to change.

  5. On the Advanced tab, select a new EVT from the Earned Value Technique group box.

  6. Click Save.