There are Vision features that affect the information that displays on the Navigator Dashboard and Planning tabs.
Contents
| Field | Description |
| Show Unposted Actual Labor
|
Navigator includes unposted actual labor values even if the Vision plan's
Show Unposted Actual Labor option is not selected.
|
| Show Committed PO Expenses
|
Navigator includes consultant and expense charges from committed purchase orders even if the Vision plan's
Show Committed PO Expenses option is not selected .
|
| Include in Utilization and Project Reports
|
If a project is mapped to multiple Vision plans and this option is selected in Vision, the Navigator totals are the combined value of the plans mapped to the project.
|
| : Enable Phases/Tasks
|
If you run a key conversion to start using the phase or task level for a project with a Navigator plan, existing planned resource rows are moved down to the new lowest level.
|
| : Disable Phases/Tasks
|
If you run a key conversion to stop using the phase or task level for a project with a Navigator plan, the following occurs:
- Existing planned labor, expenses, and consultants resource rows are moved up in the WBS.
- Planned labor rows for the same resource are combined when moved up under the same WBS ID.
- Planned consultant rows are combined when they are moved up under the same WBS ID and have the same account and vendor.
- Planned expense rows are combined when they are moved up under the same WBS ID and have the same account and vendor.
|
|
|
When a Search and Replace is performed on the Project Planning application area, Vision Navigator plans are excluded from the Plan Lookup.
|