This topic describes the KPI boxes and charts you can view in the Dashboard workspace if you selected a fixed price job.
KPI Boxes
Field | Description |
EAC Margin
|
This box displays the budgeted gross margin represented as a percentage on the fixed price of the job currently selected.
The value is computed as follows:
((Fixed Price - Cost from latest working budget)/Fixed Price)*100
iAccess displays the box in a different color, depending on the value shown:
-
Green - Above 50%
- Yellow
- Between 25-50%
- Red - Below 25%
|
Baseline Deviation, Hours
|
This box displays the deviation (in hours) from the baseline budget, based on the latest progress evaluation for the job currently selected.
If the value is a positive number, iAccess displays this box in red.
If the job currently selected has no baseline budget, iAccess leaves this box blank.
|
Customer Balance Due
|
This box displays the amount due from the customer, in base currency.
If the value is a positive number, iAccess displays the box in red. Otherwise, iAccess displays the box in green.
|
Revenue Recognized
|
This box displays the revenue recognized, in base currency.
|
Risk Profile
|
This box displays the overall risk profile level specified for the job currently selected.
|
Approved Risk Fund
|
This box displays the sum of costs from budget lines on risk-related tasks, in base currency. This is from the latest approved job budget revision.
|
Weighted Assigned Risk Fund
|
This box displays the sum of costs under the
Assigned Risk Fund
column for all job risk lines entered for the current job in the Job Risk Registers single dialog of the Workspace Client. This is displayed in the base currency specified for the job.
|
Fixed Price
|
This box displays the fixed price of the job currently selected, in the currency specified for that job.
|
Invoiced On Account
|
This box displays the total amount invoiced on account, in the currency specified for the job currently selected.
|
Open Billing
|
This box displays the total open billing price for the job currently selected, in the currency specified for that job.
|
Completion
|
This box displays the completion percentage as indicated in the latest approved progress evaluation for the job currently selected.
|
Charts
Field | Description |
Progress
|
This chart displays Actual, EAC, and Baseline Hours for the job currently selected, based on the progress evaluations created for that job within the last six months.
This information is also available in the History tab of the Progress Evaluation workspace.
|