When you use this action, Maconomy automatically creates purchase orders for those amount activities in the job budget that have a vendor number and for which the Selected field is selected. A purchase order is an order for the vendor service described by the budget line’s amount activity. The amount on the purchase order line is the cost sum on the budget line less the sum of previously created purchase order lines. If this amount is negative, the amount on the purchase order line is 0. You can only use this action if the budget shown in the window is the current one, and if the job in question has not been blocked.
Maconomy checks that none of the lines selected for purchase order creation causes budget violations according to the rules set up in the Limit Purchase Amount to Budget; Limit Purchase on Sum or Line Level; Limit Purchase, Currency Margin; and Limit Purchase, Percentage Margin job parameter attribute for the job. If just one line causes a budget violation, the action is cancelled for all lines, including lines that do not cause any budget violations.
Budget violations can occur if purchase orders already exist for the lines, and the new purchases combined with existing purchases cause the budgeted amount to be exceeded. For further information, see the descriptions of these attributes in the Budgeting job parameter.
Maconomy creates a purchase order for each combination of vendor and purchase order currency specified on the marked lines, and Maconomy assigns each of the purchase orders to a separate, new purchase process (see Purchase Processes in the A/P module). Maconomy uses the earliest date in the Planned Starting Date field on lines that have the same combination of vendor and currency as the preferred delivery date in the card part of the resulting purchase order. If there is no planned date, Maconomy uses today’s date. You can edit purchase orders in the Purchase Orders window in the Accounts Payable module.
When you create purchase orders, Maconomy updates the Number of Purchase Orders and Purchase Order Total fields on the budget lines. Maconomy then displays the purchase order number in the Last Purchase Order No. field on every budget line.
Maconomy retrieves information such as payment terms and delivery mode from the vendor information card in the A/P module.
Maconomy takes the currency of each purchase order is taken from the Currency, Purchase Creation field on the budget lines, resulting in the purchase order in question. If this field is blank, Maconomy takes the currency from the vendor’s information card. If you specified fixed exchange rate information for the job in the Job Price Information window, Maconomy applies the specified fixed exchange rate information, but only if the Fixed exchange rates in budgets only system parameter is not marked.
If you assigned texts to the job budget lines in the Job Budget Texts window, and if you marked the Text Lines for Purchase field in the Job Information window, Maconomy transfers the texts to the relevant purchase orders.
|