Job Tab
This section includes the fields and descriptions for the Job tab.
Approval Status Island
Current Job State Island
Customer Island
Company Island
Job Island
Invoicing Island
Status Island
User Island
See the chapter “Getting Started” for a description of the fields in the island User. Note, however, that until a quote, an order confirmation, an invoice, or a credit note has been printed for the current job, the field “Version No.” will always show the value 1.
Dimension Combination Island
Derived Company Island
Derived Dimensions Island
Employees Island
Extra Fields Island
Description Island
Price Island
Creation Island
Copying Island
In this island, you can specify settings for copying the current job to a new job. When you have specified the correct settings, select the “Copy Job” action to copy the job.
Approval Island
In the fields in this island, you can specify the approval procedures applying to time and expense sheet lines pertaining to the current job. For each job, you can specify whether the supervisor of an employee, the project manager of the job, both, or none of them are to approve time registrations, expense registrations, or both. The default values in these fields are transferred from the corresponding fields in the window System Information in the Set-Up module.
Note that if you want separate approval routines for time vs. expense registrations, the system parameter “Allow separate approval requirements for time and expenses” must be marked in the window System Parameters in the Set-Up module. If the parameter is not marked, the fields are mutually dependent—that is, changing the value for the Supervisor or Project Manager for time registrations changes the corresponding value for expenses, and vice versa. It is possible to change the approval principle of a job, even though time sheets or expense sheets with entries on the job have already been created. However, if any such time and expense sheets have been submitted, they must be transferred before the approval principle can be changed.
The supervisor of each employee is specified in the window Employees. A supervisor approves time and expense sheets in the windows Time Sheets and Expense Sheets, respectively.
If approval of expense sheets is performed through an approval hierarchy, this approval overrules the supervisor’s approval. This means that if it has been specified on a job that the supervisor must approve expense sheets, an expense sheet can only be posted (and thereby settled) when it has been fully approved through an approval hierarchy. If the project manager’s approval of a job is also required, the individual expense sheet lines must also be approved by the project manager before the sheet can be posted. The project manager’s approval is carried out without using approval hierarchies.
Link Jobs Island
Field | Description |
---|---|
No. of Subjobs | This field shows the number of underlying jobs assigned to the job. The value cannot be changed here. |
Main Job | In this field, you enter the number on an existing job in the Job Cost module. Maconomy only allows one level of subjobs which means that the current subjob must not have its own subjobs and that the specified primary job must not be a subjob.
If you wish to change the current job into a subjob for another job, you enter in this field the number on the job you wish to assign as the primary job. In the window Distribute to Subjobs you can specify an allocation percentage for each subjob. Printouts of information about primary jobs and subjobs can also be retrieved by using the layouts “Summary” and “Customer Summary” in the window Print Jobs or by printing out job reports in the window Print Job Report. When you print out a job report on a primary job, you can choose to |
Access Level Island
Field | Description |
---|---|
Access Level | In this field, you enter the access level to be assigned to the job. If you do not enter an access level, all users with access to the window Jobs will have access to the job.
Please note that this access control model only applies if the standard access control configuration has not been changed in your Maconomy system. If it has, the access to jobs may depend on other factors. For further information about the standard access control configuration, please see the section “Introduction to the Access Control System” in the Set-Up module. It is only possible to enter an access level if you have access to the level in question. You can assign access levels to a user in the window User Access Levels in the Set-Up module. This field also shows a description of the specified access level. |
Registration Island
Field | Description |
---|---|
Job Allocation | In this field, you can specify which allocation rule you wish to use in connection with job reporting. Allocation rules can be created in the window Job Allocation Combinations. |
Employee Control | In this field, you can specify the way in which you want to check which employees can be used in entries on the job. This is useful to avoid accidental, incorrect entries.
The check is performed in all windows in which you can enter, reallocate, or import job entries or purchase orders. Maconomy will default to the control type specified for the current job group, but you can change the control type for each job in this field. There are the following options:
Of these methods for employee control, the “Employee List” method is recommended over the “Budget” method, as the planning budget is likely to be needed for other purposes, such as for resource planning where specific employee assignments are discouraged. For more information, please see the description of the window Employee Control. |
Task List | In this field, you enter the task list assigned to the job. |
Budgeting Island
Field | Description |
---|---|
Hours Per Man Day | In this field, you can specify how many hours are in a man day. In the table part, quantities for time activities can be specified either as a number of hours or a number of days. There are separate fields for specifying hours and days. When you specify a number of days, the corresponding number of hours is automatically calculated by multiplying the number of days by the value in this field. Similarly, when you specify a number of hours, the corresponding number of days is calculated by dividing the number of hours by the value in this field.
This field is also used for calculating prices per day from hour-based prices. This field is also used when converting quantities of time from hours to days or vice-versa. When transferring time from a time sheet in days, the quantity is multiplied with this field to get the number of hours (if time on the job is measured in hours). |
Time Budget In Days | Select this check box to show quantities in the Time Budget workspace in days. The default value is not selected, which shows quantities in hours. Maconomy updates this field when you change the value of the Time Unit field; the Time Budget In Days field is selected if you choose Day for the time unit, and deselected if you choose Hour for the time unit. |
Customer Job Option Lists Island
Copy to come.
Budget Status Island
Field | Description |
---|---|
Current Budget | For information about budgets, refer to the Job Budgets single dialogs workspace. |
Exists | This field specifies whether the current budget already exists for the current job. |
Planning Budget | For information about budgets, refer to the Job Budgets single dialogs workspace. |
Exists | This field specifies whether the planning budget already exists for the current job. |
Forecast Budget | For information about budgets, refer to the Job Budgets single dialogs workspace. |
Exists | This field specifies whether the forecast budget already exists for the current job. |
Baseline Budget | This field shows the budget type of the baseline budget on the job. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialogs workspace. |
Exists | This field specifies whether the baseline budget already exists for the current job. |
Fixed Price Budget | This field shows the budget type of the fixed price budget on the job. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialogs workspace. |
Exists | This field specifies whether the fixed price budget already exists for the current job. |
Completion Percentage Budget | This field shows the budget type to use when calculating the completion percentage of the job. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialogs workspace. |
Exists | This field specifies whether the completion percentage budget already exists for the current job. |
Baseline Comparison Enabled | This field shows whether baseline comparison is enabled on the job for assessing job progress. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialogs workspace. |
Fixed-Price Basis | This field determines whether the fixed price of a job is transferred from the latest approved job budget type or from the job's quote. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialogs workspace. |
Rec. Rev. By Compl. Percentage | This field shows whether revenue on a job should be recognized according to completion percentage. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialog workspace. |
Handling of Overruns | This field shows whether the specified job should handle overruns. For more information about how this job parameter is utilized with jobs, refer to the Job Parameters single dialog workspace. |