Job Progress Single Dialogs Workspace
Use this workspace to create an overview of the progress of jobs and see whether they are on track in terms of time and cost.
This workspace shows the historic development of the progress of a job budget, compared with actual entries on the job. The Job Progress tab displays information about the current job. The Job Budget Lines sub-tab contains budget lines with information about the activity, task, and employee category that are associated with each planning budget line.
A historic entry is created when you create a progress estimate. This enables you to re-estimate one or more tasks and approve the budget again. The approved estimate is also taken into account in the detailed planning in the Resource Planning module.
The progress estimate is based on the job's planning budget. You select the planning budget for it in the Job Budgets workspace. Use the Planning job parameter type to set the job up to compare the job's progress with an additional budget, the baseline budget.
A baseline budget is typically used for storing the budget on which a contract is based, and is rarely changed. However, if the job changes scope, such as when you are requested to perform new tasks in addition to those already on order, you should also update the baseline budget. If you were only measuring job progress based on the regular planning budget, a deviation between the planned work and the actual work would occur, and it would not be immediately apparent that the extra work was performed due to a scope change. By comparing with the baseline budget as well, the deviation can be explained by the job scope change.
The progress of a job can be measured by the amount of hours spent on the job or by the total cost incurred on the job. The amount of hours is collected from job entries on time activities. The amount of costs is collected from job entries on amount activities and from the cost of entered time activities.
The Progress island in the Job Progress tab contains lines with history entries that display the five most recent progress estimates.
The Job Budget Lines sub-tab displays the quantity of hours or the amount planned for the line, the number of hours completed, the estimated completion requirement of the budget line, and the date on which this information is considered valid. If the budget has been structured hierarchically, group headers display summarized information from their subordinate lines. You cannot enter information directly on group header lines. To further examine each planning budget line, the project manager can use the Task Progress workspace, which shows information on each budget line, as well as any estimates for the requirements for completion as per the entries entered on the job.
The Job Budget Lines sub-tab shows the progress status of the latest estimate shown in the Job Progress tab. If you want to see the updated progress information for each of the job budget lines, enter a date in the Progress island in the Job Progress tab to indicate the date through which you want to measure progress for this job. Maconomy then performs a calculation of the progress estimates as of that date and show the updated progress information in both parts of the workspace
If the job budget currently displayed in this workspace is approved, most fields appear closed. Since re-estimating a job budget in this workspace changes the budget, you can only do that if the budget is not yet approved. If the budget is approved, you can reopen it in this workspace using the Reopen Planning Budget action.
You can choose to re-estimate either the entire job or just one or several of the planning budget lines shown in the Job Budget Lines sub-tab. To re-estimate the entire job, enter a new estimated time or amount to completion along with an estimate date on the last line in the table in the Progress island. Depending on whether you have selected the Get Est. to Compl. from All Resources field in the Time To Completion Estimates island, Maconomy performs a calculation to find the number of planned and completed hours for each job budget line since the last estimate date, as well as any new estimates provided by time sheet users. Maconomy can also find the number of planned and completed hours for each job budget line for all of those employees who have entered an estimated time to completion at a given time on the relevant job.
If you choose to re-estimate only one of the planning budget lines shown in the Job Budget Lines sub-tab, you can enter a new estimate for the selected line. The total estimate of the job is automatically written up/down accordingly. Similarly, the total estimate is reflected in the Quantity field on the planning budget line in the Job Budgets workspace.