The Weekly EOC Detail report displays data at the detail WBS level. The Weekly EOC Rollup report displays data at any level of the WBS.
These reports will include data even if weekly data has never been posted. If you run the report before posting data and select the At Complete Values option, at complete values will be included in the report. If you select the Cum from Inception option, cumulative values will be reported.
You may include a maximum of 12 weeks on a Weekly EOC report. If the report start and report end you select encompasses more than 12 weeks, you will get an error.
Access the Weekly Report Conditioning Window by selecting Weekly on the Reports tab. To view conditioning options for the Weekly EOC reports, set Report Type to either EOC Detail or EOC Rollup.
You can limit these reports to include:
a particular WBS leg, element type, or level of the WBS.
specific WBS Aliases, Managers, Cross-References, recurring/nonrecurring items.
OBS performing/responsible departments, a specific department, a specific CLIN.
You can also choose to include in these reports:
Report Timeframe:
Incremental
Cumulative
At Complete Values
Elements of Cost
Cost Elements:
EQP
Standard Hours
Hours
Prime
Overhead
Total Burdened
G&A
Total Cost
Cost of Money
Total Dollars
Fee
Total Price
These options are displayed as check boxes for each individual combination, for example Overhead (EOC Section) prompts if you want to add a subtotal for Overhead to the EOC section of the report. Place check marks next to all totals and subtotals you want to include.
Element Types:
BCWS
BCWP
ACWP
SV
CV
SPI
CPI
ETC
You can choose to calculate cumulative values from Inception (Project Start date) or Report Start (the Report Week date you select under Report Timeframe)
You can add Page Breaks between WBS Elements if desired.
This report uses the projectnameU.RRH, projectnameW.RRD, projectnameP.WBS, and projectnameF.WRD files.