If you shifted Resources, you may also want to shift your Milestone schedule and forecast dates to correspond to the new start and complete dates.
To shift the milestone schedule dates, click the Shift Milestones — Schedule Dates checkmark box. To leave the schedule dates unchanged, leave this box empty. This option is only available if you selected Shift Baseline or ETC Resources.
If you select Baseline Update and Shift Milestones, the milestone dates are shifted the same number of days that the baseline has been shifted.
If you select ETC Update and Shift Milestones, the milestone dates are shifted the same number of days that the ETC has been shifted.
If you select both Baseline and ETC Update and Shift Milestones, the milestone dates are shifted the same number of days that the baseline has been shifted.
To shift the milestone forecast dates, click the Shift Milestones — Forecast Dates checkmark box. To leave the schedule dates unchanged, leave this box empty. This option is only available if you selected Shift Baseline or ETC Resources.
If you select Baseline Update and Shift Milestones, the milestone dates are shifted the same number of days that the baseline has been shifted.
If you select ETC Update and Shift Milestones, the milestone dates are shifted the same number of days that the ETC has been shifted.
If you select both Baseline and ETC Update and Shift Milestones, the milestone dates are shifted the same number of days that the baseline has been shifted.
If you have elected to update and shift resources, MPM must reprice after it shifts the estimates.
The EOC Reprice Conditioning portion of the WBS Schedule Import Conditioning window lists all EOCs stored in the EOC table. For each EOC, select from the list box the value you want maintained constant for repricing: Hours, Equivalent Persons, Prime Dollars, Total Burdened, Total Cost, Total Dollars, Total Price, and Original Estimate Type.
If dates are being updated for WBS elements with no estimates (no shift required), only those WBS elements that start after Time Now are updated. If dates are being updated for WBS elements with estimates and resources are also being shifted, only those estimates that start after Time Now are shifted.