After selecting an EVM for the WBS element, you must select a BCWP Base. The BCWP Base shows which unit MPM will use to calculate the BCWP for a WBS element. The BCWP Base unit should match the Estimate Type in the Integrated Planning Baseline window. You can choose from five base units:
Hours/Units
Prime Dollars
Total Burdened (Prime + Overhead)
Total Cost (Total Burdened + G&A)
Total Dollars (Total Cost + COM)
Total Dollars is the default value.
To select the BCWP Base, complete the following steps:
Click the BCWP field to display the drop-down list box.
Select a BCWP Base from the list.