Selecting a BCWP Base

After selecting an EVM for the WBS element, you must select a BCWP Base. The BCWP Base shows which unit MPM will use to calculate the BCWP for a WBS element. The BCWP Base unit should match the Estimate Type in the Integrated Planning Baseline window. You can choose from five base units:

Total Dollars is the default value.

To select the BCWP Base, complete the following steps:

  1. Click the BCWP field to display the drop-down list box.

  2. Select a BCWP Base from the list.