The Responsibility Assignment Matrix report graphically illustrates the WBS/OBS matrix and prints the dollar budget (BAC) associated with each intersection. You can use this report to reference the budgets represented by the WBS/OBS relationships. This report is often referred to in government C/SCSC demonstrations and Subsequent Applications Reviews (SARs).
Access the Responsibility Assignment Matrix Report Conditioning Window by selecting Responsibility Assignment Matrix on the Reports tab.
You can limit this report to include only:
a particular WBS leg, element type, or level of the WBS
specific WBS Aliases, Managers, Cross-References, recurring/nonrecurring items
OBS performing/responsible departments, a specific department, a specific CLIN
You choose which Cost Element to depict in this report:
Hours
Prime Dollars
Total Burdened
Total Cost
Total Dollars
Total Price
This report uses the files projectnameU.RRH and projectnameW.RRD.