Most of the fields in the Milestone display are read only, with the information pulled from other areas of MPM. The editable fields are:
|
|
|
|
|
|
|
|
|
|
To edit a milestone, complete the following steps:
Select the field you want to edit.
Make the change. When you change a field value, MPM changes the color of the text of the WBS and the text of all of the milestones for the WBS to blue. The blue color indicates a milestone has been changed but not saved.
To save the change, do one of the following:
Click on another WBS element row in the window.
Click Save
Click File » Save
Press Ctrl+S
You may be prompted to confirm the save. If you do not want to save the changes, press Esc.
Other editing functions are covered in the following subtopics: