You use the BCWP Status window to export BCWP data. Access the BCWP Status Export Conditioning Window by selecting BCWP Status on the Exports tab. MPM displays the BCWP Status Export Conditioning Window.
When exporting BCWP, all data conditioning options described in Project Export Conditioning Options are available to condition the data being exported. In addition, you can specify the following options:
Display Percentages (optional) — Use this output option to choose whether to export percentages as decimal values (.5050) or as a percent (50.50).
Earned Value Method (optional) — To select data assigned to a particular EVM, click in the Criteria box and select from the drop-down list containing all possible EVMs.
You can use the standard BCWP.FMT format file or create a custom file using the fields listed below.
For information on creating custom format files, see Creating Format Files.
BCWP Fields |
WBS Fields |
Month-Year (in YYYYMM format) |
WBS (ID) |
Percent Complete |
Parent WBS |
Total BCWP |
Alias |
WBS Description |
|
Manager |
|
Xref-1 |
|
Xref-2 |
|
Xref-3 |
|
Xref-4 |
|
Xref-5 |
|
Xref-6 |
|
Xref-7 |
|
Xref-8 |
|
Xref-9 |
|
Xref-10 |
|
Performing Department |
|
Responsible Department |
|
Charge Number |
|
Element Type |
|
Baseline Start |
|
Baseline Complete |
|
ETC Start |
|
ETC Finish |
|
Early Start |
|
Early Finish |
|
Late Start |
|
Late Finish |
|
Revision Letter Date |
|
Schedule Reference Date |
|
Last Statused Date |
|
Total Float |
|
EV Percent Complete |
|
Recur/NonRecur |
|
Fee Percent |
|
Fee Limit |
|
Earned Value Method |
|
BCWP Base Unit |
|
CLIN |
|
Base WBS |