DPCU does four different validations during the conversion process. They are:
Does the Target Project exist?
Does the Target WBS exist?
Does the Target WBS have a Resource identified in the WBS Lookup field indicated?
Does the Target WBS have a value in the Charge Number field?
At the end of the conversion process, a log file will be generated. If any of the above validations are not met, then the log file will indicate which validations were not met and for which XFR file.
The log file can be viewed two different ways:
If there were validations not met during the conversion process, DPCU will indicate so when the conversion process is complete.
The other way to view the log file is from the Utilities Tool Bar. Under Utilities, select “View Log File.”