Whenever you need to calculate Budgeted Cost of Work Performed (BCWP), you use the Calculate BCWP utility in Project Maintenance. For example, whenever you modify milestone information in Integrated Planning, you will want to calculate a new BCWP.
When calculating BCWP, you can apply the following restrictions:
Limit the date range
Select different sets of WBS elements
If you select this option: |
MPM calculates BCWP for: |
All WBS elements |
All WBS elements |
Statused, LOE, Key Event & Apportioned WBS Elements |
|
Only Statused & Apportioned WBS Elements |
Same as above, except LOE and Key Event elements are included only if they have been statused. |
When you calculate BCWP, Fee is not calculated because it does not apply to BCWP.
MPM always calculates a WBS percent complete for all elements in the WBS hierarchy regardless of the WBS Element option you choose.
Any change to the budget after WBS elements have been statused will have an impact on the calculation of BCWP. For information on budget changes, refer to Impact of Budget Changes on BCWP Values.
To calculate BCWP for a project, complete the following steps:
In the Project Maintenance window, select a project.
Click Tools » Calculate BCWP. MPM displays the BCWP dialog box.
Enter the From and Through dates. Enter the dates in the MMM YY format.
Select one of the WBS element options.
Initiate the calculation by choosing OK.