Refresh PRSummary Table
You can run this utility at any time. Deltek recommends that you schedule it to run every night or during off-hours. If you do so, numbers on the reports are accurate as of the preceding night, for all users.
You can schedule this process via the process server.
To run the Refresh PRSummary Table utility:
- On the Navigation menu, click .
-
On the Refresh Project Summary Table form, select one of the following actions:
Option Description To run the utility manually Click Run. To schedule the utility to run on a regular basis via the process server Click Schedule and complete the information on the Schedule dialog box.