Reassign a Consultant Type Assignment in a Project Plan
If you assign a consultant type to a work breakdown structure (WBS) element in a project plan and later want to change the assignment to another consultant type or consultant name, you can do so from the Consultants tab of the Projects form. You can also change the consultant's name for an consultant type assignment.
To reassign a consultant type assignment to another consultant type or consultant name:
-
In the Navigation pane, go to the
Hubs section and click
Projects.
- Select the project for which you want to make the reassignment.
- Switch the Project/Plan toggle to Plan.
- On the Actions bar, click .
- Click the Consultants tab.
- Expand the WBS to display the consultant type assignment row that you want to reassign.
- Hover over or click that row and click at the end of the row.
-
Click
Reassign.
Result: The Reassign Consultant Type and Consultant Name dialog box displays.
- To reassign to a different consultant type, select that consultant type in Consultant Type.
- To reassign to a different consultant, select that consultant's name in Consultant Name.
-
Click
Reassign.
DPS does the following:
- Reassigns the planned amount to the consultant type and consultant's name that you selected.
- Deletes the original assignment. (The original assignment is not deleted if an actual job-to-date (JTD) amount exists for that assignment, or if that assignment was saved as part of the plan baseline.)