If planning is enabled for expenses, use the Expenses tab on the Plan Settings dialog box to specify the planning level and the billing rate methods, tables, and multipliers for expenses.
Contents: General
Field | Description |
Planning Level
|
Use this drop-down list to select the planning level at which you will plan expenses for the
project:
- Plan Level 1, Plan Level 2,...: Plan expenses at the specific level you select. Lower numbers are higher in the plan structure. For example, for a
project plan, level 1 corresponds to the
project level of the work breakdown structure (WBS). If the plan structure has branches that do not extend down to the selected level, you can plan expenses at the lowest levels in those branches.
- Lowest Level: Plan expenses at the lowest level of each branch of the plan structure. For example, if the lowest level is level 2 for one branch and level 3 for another, you enter expense plan data for the first branch at level 2 and for the second branch at level 3.
|
If you later change the planning level and planned expenses exist at a level lower than the new planning level,
DPS notifies you that those planned expenses must be removed before the change can occur.
Contents: Reimb. Expense Billing Markup
Use these fields to define the settings for reimbursable expense planned amounts on Regular
projects.
If you select
Cost in
Budget Type on the General tab of this dialog box, or the
Use Billing Currency not
Project Currency option is selected on the Accounting System Settings form in the
DPS desktop application and the
project currency is not the same as the billing currency,
Billing Rate Method automatically defaults to
None
and
Expense Rate Method,
Rate Table, Recalculate Planned Billing, and
Billing Multiplier fields are display-only.
Field | Description |
Recalculate Planned Billing
|
Under normal circumstances, you never need to select this check box. When you save settings for a plan, all plan assignments are automatically recalculated based on the current settings.
The exception is if the plan was converted from iAccess to
DPS. Converted assignments may have rate information that was saved for specific calendar periods while in iAccess. Following conversion, those plan amounts, by default, are not automatically recalculated when you save plan settings in
DPS. If you want all planned reimbursable expense billing amounts in the plan to be recalculated automatically, select this check box and then save the plan settings. You only need to do this once; from that point forward the reimbursable expense billing amounts will be recalculated automatically each time you save settings.
|
Expenses Rate Method
|
Select one of the following as the expense billing rate method for the plan:
- Multiplier Only: Use a multiplier without a rate table: Planned cost x Billing multiplier.
-
From
Account Rate Table: Use the rate for the expense
account from an expense
account rate table. If no rate is found, use Planned cost x Billing multiplier.
-
From Category Rate Table: Use the rate for the expense category from an expense category rate table. If no rate is found, use Planned cost x Billing multiplier.
-
None: The planned billing amount is set to the planned cost.
|
Rate Table
|
If you selected an expense billing rate method other than
Multiplier Only or
None, select an expense billing rate table for the plan.
The only rate tables displayed for selection are those that match the rate method you selected (expense
account tables or expense category tables) and that are marked as available for planning.
|
Billing Multiplier
|
If you selected
Multiplier Only in
Expenses Rate Method, enter a multiplier for calculating billing amounts for reimbursable expenses (1.2500, for example). If you selected
From
Account Rate Table or
From Category Rate Table in
Expenses Rate Method, enter a multiplier to use for calculating billing amounts if the specified rate table does not include a rate for the expense
account or expense category.
|
Contents: Direct Expenses
Field | Description |
Direct Expenses: Billing Multiplier
|
The multiplier is displayed for informational purposes only on Regular
projects. The value is always
1.0000 and cannot be changed. The planned cost and planned bill amounts for direct expenses are always the same.
|
Contents: Indirect Expenses
Field | Description |
Indirect Expenses: Billing Multiplier
|
The multiplier is displayed for informational purposes only on Overhead and Promotional
projects. The value is always
1.0000 and cannot be changed.
|