Delete a Resource Assignment in Project View
If you assign a resource to work on a project and later want to remove that assignment, you can do that in the Project View grid.
You can also delete resource assignments in the Resource View grid or on the Labor tab of the Projects form.
If the assignment has job-to-date (JTD) hours or has been saved as part of the baseline plan, you cannot delete the assignment. In those cases, however, you can still use the procedure below to delete all planned hours for the assignment.
To delete a resource assignment in Project View:
- In the Navigation pane, go to the Resource Management section and click Project View.
- Select the project for which you want to delete an assignment.
- Expand the work breakdown structure (WBS) until the resource assignment row is visible.
- Hover over that assignment row and click at the end of the row.
- Click Delete.
- When the confirmation message displays, click Delete again.