Field | Description |
Report Name
|
You can change the default report name.
|
Format
|
Select the type of data the report displays for each employee:
-
Hours
-
Cost Amount
-
Billing Amount
-
Revenue
-
Percentage: Select this option to display the ratio of employee actual hours to expected hours for each period, expressed as a percentage. For example, if an employee's expected number of hours for a period is 40 and she works 50 hours, the report displays
125 (125%) for that period.
-
Alerts: To identify deviations from the expected working hours for employees, select this option and enter a percentage in
Standard Utility Percentage.
- The report displays
OVER for a period for employees whose hours exceed the expected hours by more than the percentage in
Standard Utility Percentage.
- The displays
UNDER for a period for employees whose hours are less than the expected hours by more than the percentage in
Standard Utility Percentage.
You specify expected hours in the
Hours/Day field on the Personal tab of the Employees hub.
If you select
Alerts, also enter a percentage in
Standard Utility Percentage.
If you select
Percentage or
Alerts,
Deltek takes into consideration the holidays and non-working days in Resource Planning Settings when it calculates expected hours.
Your access to labor cost rates and amounts may be restricted by role security.
|
Standard Utility Percentage
|
If you set
Format to
Alerts, enter a percentage in this field to indicate how far an employee's actual hours can vary from the expected hours before it results in an alert on the report.
Example: In the
Standard Utility Percentage field, you enter
10. The number of expected hours for an employee for a period is 100 hours.
- If the employee works 85 hours, the report displays
UNDER for that period. The actual hours are more than ten percent less than the expected hours.
- If the employee works 95 hours, the report displays
OK for the period. The actual hours are less than the expected hours, but the variance is only five percent.
- If the employee works 112 hours, the report displays
OVER for the period because the actual hours are over ten percent more than the expected hours.
If you do not enter a percentage, the report displays
UNDER or
OVER for any variance from the expected hours.
|
Period Scale
|
Select one of the following period scales for the hours or amounts on the report:
-
Daily
-
Weekly
-
Bi-Weekly: A two-week period.
-
Semi-Monthly: One semi-monthly period runs from the first to the fifteenth of the month. The second semi-monthly period runs from the sixteenth to the end of the month.
-
Monthly
-
Accounting Period
-
Quarterly
-
Yearly
|
Start Day of the Week
|
If you set
Period Scale to
Weekly or
Bi-Weekly, use this field to specify the starting day of the week.
|
Range
|
Select the number of reporting periods to display. The related
Period Scale option determines the type of period. For example, if the period scale is monthly and you enter 6 here, the report displays data for six monthly periods.
|
Decimal Setting
|
Select the number of decimal digits to display for hours or amounts.
If you set
Format to
Hours, select one of the following settings:
-
No Decimal: The report displays the number of hours without decimal digits.
-
1 Digit: The report displays the number of hours with one digit to the right of the decimal point.
-
2 Digits: The report displays the number of hours with two digits to the right of the decimal point.
If you set
Format to
Cost Amount,
Billing Amount, or
Revenue, select one of the following settings:
-
No Decimal: The report displays amounts without decimal digits.
-
Currency: The report displays amounts with the number of decimal digits specified for the currency on the Currency Configuration form ().
|
Column Width
|
Enter the width of each of the period columns in inches or millimeters based on which one you selected in the
Unit of Measure field on the Layout tab.
|
Start Date
|
Select the starting date for the data on the report:
-
Today: The report displays data starting with the current date.
-
Specific Date: The report displays data starting with the date that you specify.
|
Exclude Non-working Days
|
If you set
Period Scale to
Daily, select this check box if you do not want the report to display reporting period columns for the non-work days specified in the company calendars. The primary purpose of this option is to reserve space on the report for work days.
|
Apply Plan Probability to All Amounts
|
Select this check box if you want
Deltek to include plan probabilities when it calculates plan amounts. For example, if the plan probability is 50%, the amounts that the report displays for the plan are 50% of the original amounts.
|
Only Include Plans Marked for Utilization and Project Reports
|
If you select this option, the report includes only those plans that you select on the Plan lookup for which the
Include in Utilization and Project Reports option is selected on the General tab of the Project Planning form.
If you do not select this option, the report includes all plans that you select on the Plan lookup.
|
Only Include Mapped Plans
|
Select this option to only include plans that are mapped to projects. To map a plan to a project, you connect a plan's elements to existing or to-be-created projects, phases, and tasks. As you charge actual time and expenses to the project,
Deltek automatically updates your plan with those hours and amounts.
|