Labor Plan EVT Charts Columns

The Labor Plan EVT Charts report contains a standard set of columns. You cannot select columns for this report.

Columns

Column Description
Period in Chart This column displays the period from chart.
BCWS This column displays the budgeted cost of work scheduled for the period. These amounts are based on planned amounts or on baseline amounts, depending on the option that you select in For BCWS, Show on the General tab.
ACWP This column displays the actual cost of work performed for the period. Deltek displays graphed values based on actual job-to-date amounts as a solid line and displays graphed values based on estimate-to-complete amounts as a broken line.
BCWP This column displays the budgeted cost of work performed for the period.