Use the General tab to select the budget source and select the actuals rate for project information. These options are saved
Contents
Field | Description |
Budget Source
|
If your enterprise uses the Planning application, you can select the source of budgeted amounts:
-
Budget Worksheet: The source is the budget worksheet in the Accounting application.
-
Project Planning: The source is a mapped plan in the Project Planning application.
|
Identify Projects that have Unpublished Changes
|
Select this option to identify any project that has a plan with unpublished changes. When this criteria is met, a
Caution indicator displays next to the project number in the Project Review context area to alert you that there may be more current data.
|
Basis for Planning Calculations
|
Use this option to set the date on which Project Planning is selected as your budget source. Select one of the following settings:
-
Today's Date: The date is set to the current date.
-
Period End Date: The date is based on the last day of your enterprise's current accounting period.
-
Specific Date: You enter or select the date here.
|
Show Cost Analysis
|
Select the rate used to calculate the actuals displayed on the Project Review form:
At Cost or
At Burden.
|
Estimate Overhead
|
If this field is selected, overhead is estimated according to the settings in Overhead Configuration, for the period in which overhead allocation has not yet been run.
|
Include Unposted Time
|
Select this option to include hours from timesheets that have not yet been posted.
|
Exclude Reimbursable Expenses
|
Select this option to exclude reimbursable expenses from the Project Review form.
|
Exclude Reimbursable Consultant Expenses
|
Select this option to exclude reimbursable consultant expenses from the Project Review form.
|
Exclude Direct Expenses
|
Select this option to exclude direct expenses from the Project Review form.
|
Exclude Direct Consultant Expenses
|
Select this option to exclude direct consultant expenses from the Project Review form.
|