Effective Dates and Cost Rates Hierarchy
After you create cost rate tables, you can associate the tables with individual projects, employees, or both. The cost method that you choose when you associate a cost rate table with a project or employee determines how Deltek applies cost rates for employee timesheet transactions and billing transfers when those transactions are posted to your projects.
- Projects Hub: Associate cost rate tables with your projects using the Cost Method and Cost Table fields on the Accounting tab of the Projects hub. Specify a different cost rate method, table, or both at each level of a project's work breakdown structure.
- Employees Hub: Associate cost rate tables with employees using the Cost Method and Cost Table fields on the Time tab of the Employees hub. The cost rate method and table selections on this tab override the cost rate information that is entered on the Accounting tab of the Employees hub.
Cost Rates Hierarchy
When you post employee timesheet transactions to a project, Deltek looks first at the project record and then at the employee record (if necessary) to determine how to apply cost rates.
Deltek uses the first setting it finds, based on the following hierarchy:
- Projects hub record for task: Cost Method field on the Accounting tab.
- Projects hub record for phase: Cost Method field on the Accounting tab.
- Projects hub record for project: Cost Method field on the Accounting tab.
- Employees hub: Cost Method field on the Time tab.
- Employees hub: Job Cost Rate field on the Accounting tab.
Project Cost Rate Methods (Hierarchy Levels 1 through 3)
Because
Deltek looks first at the
project record, the options that you select in the
Cost Method field on the Accounting tab of the
Projects hub (at the lowest level of the work breakdown structure) determine how cost rates are applied. The options are:
- None: This is the default option. When you select this option, Deltek moves up the work breakdown structure and uses the first Cost Method specified (if any), for the project.
- From Employee Cost Rate: When you select this option, Deltek uses the cost rate that is specified for the employee in the Employees hub.
-
From Labor Rate Table,
From Category Rate Table,
From
Labor Code Table: When you select one of these options:
- And the employee is not covered by the table selected in the Rate Table field, Deltek uses the cost rate that is specified for the employee in the Employees hub.
- And the employee is covered by the table selected in the Rate Table field, Deltek uses the employee's cost rate from the table, if the timesheet detail date is on or after the effective date specified on the table. If the timesheet detail date is before the effective date specified on the table, Deltek uses the cost rate specified in the Employees hub.
- And the employee is covered by the table selected in the Rate Table field, but no effective date is specified for the employee, Deltek uses the employee's cost rate from the table, regardless of the timesheet detail date.
Employee Cost Rate Methods (Hierarchy Levels 4 through 5)
Based on your selections at the
project level,
Deltek may or may not consider the
employee's record in the
Employee hub.
Deltek considers the
employee record if any of the following apply:
- The Cost Method for all levels of a project's work breakdown structure is set to None.
- The Cost Method for the project is set to From Employee Cost Rate.
- The employee is not covered by the Labor Rate Table, Category Rate Table, or Labor Code Table specified for the project.
If
Deltek looks at the
employee record, the option that you select in the
Cost Method field on the Time tab of the
employee record determine how cost rates are applied. Your options are:
- None: This is the default option. When you select this option, Deltek uses the employee's cost rate as specified in the Job Cost Rate field on the Accounting tab of the Employees hub.
-
From Labor Rate Table,
From Category Rate Table,
: When you select one of these options:
- And an effective date is specified for the employee, Deltek uses the employee's cost rate from the table, if the timesheet detail date is on or after the effective date that is specified on the table. If the timesheet detail date is before the effective date specified on the table, Deltek uses the cost rate that is specified on the Accounting tab of the Employees hub.
- And no effective date is specified for the employee, Deltek uses the employee's cost rate from the table, regardless of the timesheet detail date.