Bill Fee-Based Contracts by Billing Phase
For projects with fee-based contracts, you can set up fee billing phase terms to allow for partial billing of the total fee based on the amount of work completed.
Prerequisite: You must select the Enable Posting by Billing Phase option on the Fees tab of the Billing Terms form before you can bill a fee-based contract by billing phase.
To bill a project by billing phases:
- From the Navigation menu, click .
- Open the project that you want to bill using fee phases.
-
On the Fees tab, In the
Fee Method field, select one of the following options:
- Percent Complete by Phase, as Percent of Fee.
- Percent Complete by Phase, as Fixed Amount.
- Click Insert on the Billing Phases grid to add billing phases. You can also create a new phase by copying and modifying an existing phase.
- Complete the information on the Billing Phases grid.
- Click Save.