Display the Reassign Dialog Box in Resource View

You display the dialog box from the Resource View grid row for the assignment that you want to reassign.

  1. In the Navigation pane, go to the Resource Management section and click Resource View.
  2. Use a search to display, in the grid, the resource from whom you want to reassign plan hours to another resource.
  3. Do one of the following:
    • If you are reassigning a single assignment, expand the work breakdown structure (WBS) until the assignment is visible.
    • If you are reassigning all assignments under a parent WBS element, expand the WBS until the parent element is visible.
  4. Do one of the following:
    • If you are reassigning a single assignment, hover over that WBS row and click at the end of the assignment row.
    • If you are reassigning all assignments under a parent WBS element, hover over the parent WBS row and click at the end of the row.
  5. Click Reassign.