Specify Scheduled Thresholds

To specify the target range for scheduled percentage, go to the Resource Settings tab on the Resource Planning Settings form.

If your enterprise sets up multiple companies in Deltek, these settings apply to all companies.

To specify the target range for scheduled percentage:
  1. In the Navigation pane, go to the Settings section and select Resource Planning.
  2. Click the Resource Settings tab.
  3. On the Scheduled Thresholds slider, drag one indicator along the scale to the lowest scheduled percentage of available hours that is considered properly scheduled.

    For example, drag the indicator to 95% if 95 percent or higher of employees' available hours must be scheduled to be considered properly scheduled. Employees with a scheduled percentage below 95 percent of their available hours will be considered underscheduled.

  4. Drag the other indicator along the scale to the highest scheduled percentage of available hours that is considered properly scheduled.

    For example, drag the indicator to 105% if 105 percent is the maximum percentage of employees' available hours that can be scheduled to be considered properly scheduled. Employees with a scheduled percentage above 105 percent of their available hours will be considered overscheduled.

  5. Click Save.