Use the Alternate Work Center subtask to view an alternate work center for the operation.

The alternate work center is displayed if the work center used in the selected operation has been set up of having one. You can establish work centers in the Maintain Work Centers screen.

Contents

Field Description
Alternate Work Center View other work centers that can be used in place of the designated work center for the operation.
Description This column displays the description for the alternate work center.
Process Type This column displays the type of process.
Work Center Type Description This column displays the description of the work center type.
Load Highlight an alternate work center and click the Load button to change the default work center on the main screen.

Table Information for the Alternate Work Center Subtask

Changes to the Alternate Work Center subtask updates several tables.